2020
Develop Wood-based Biomass Power Plant in Gifu Prefecture
-Operations Scheduled to Commence in March 2023-
Sep. 25. 2020
雷竞技app怎么样
Chubu Electric Power Co., Inc.
Marubeni Corporation (hereinafter, ”Marubeni”) and Chubu Electric Power Co., Inc (hereinafter “Chubu Electric”) established a special purpose company, “Gifu Seino Green Power LLC (hereinafter, “GSGP”) to develop a wood-based biomass power plant, “Godo Biomass Power Plant” in Godo Town, Anpachi ,Gifu Prefecture. In addition, today, GSGP signed a Pollution Control Agreement with Godo Town, and a Loan Agreement with Ogaki Kyoritsu Bank, Ltd. and Juroku Bank Ltd.
This project is to construct and operate a wood-based dedicated biomass power plant with a power generation output of 7,500 kW that mainly uses unused thinned wood produced in Gifu Prefecture.
In the future, based on the Pollution Control Agreement, we will work closely with Godo Town on pollution prevention and environmental conservation efforts, and aim for the start of power plant operations in March 2023 with the understanding and cooperation of the local people and other related parties.
Place | 2245-10, Godo Town, Anpachigun, Gifu Prefecture etc. Teijin Co., Ltd., on the premises of the Ibigawa Plant |
Power Generation Output | 7,500kW |
Estimated annual power generation | 一个pproximately 53 million kWh (equivalent to approximately 17,000 ordinary households) |
Fuel Type | Wood Chips |
Construction Start Date | October, 2021 |
Commercial Operation Date | March, 2023 |
Established | September, 2020 |
Head Office | 2-7-1, Nihonbashi, Chuoku, Tokyo |
Representative | Officer Performing Duties Seishi Narita(Marubeni Clean Power Corporation) |
Business | Construction of wood-based biomass power plant, supply and sale of electricity etc. |
Investment | Marubeni Clean Power Corporation※(50%), Chubu Electric(50%) |
※Marubeni has invested in GSGP through its wholly owned subsidiary Marubeni Clean Power Corporation